Report #113 โ Submitted 2026-08-18 19:08:18
| No | Observation | Status |
|---|---|---|
| โ No observations recorded โ | ||
| Furnace | Mass Received (Ton) | Consumed (Ton) | Metal Added (Ton) | Mass End of Shift (Ton) | Remarks |
|---|---|---|---|---|---|
| HA
min: 28T
|
0.00 | 0.00 | 0.00 | 0.00 | โ |
| HC
min: 24T
|
16.00 โ Below minimum
|
14.23 | 17.66 | 19.43 | โ |
| SWM1 | 31.50 | 17.66 | 17.76 | 31.60 | โ |
| SWM2 | 0.00 | 0.00 | 0.00 | 0.00 | โ |
| Stage | Condition | Comments |
|---|---|---|
| Received | Acceptable | โ |
| Hand Over | Acceptable | โ |
| M/C No. | Status | Mold Type | NDT OK | HC & FC Reject | NDT Reject | Total | Rejection % | H&F Rej % | NDT Rej % | Remarks |
|---|---|---|---|---|---|---|---|---|---|---|
| 4 | Running | 640-17 | 71 | 5 | 7 | 83 | 14.5% | 6.0% | 8.4% | flash issue |
| 5 | Running | CA90-24 | 58 | 6 | 3 | 67 | 13.4% | 9.0% | 4.5% | rework done several time |
| 6 | Running | CV98-20 | 67 | 4 | 0 | 71 | 5.6% | 5.6% | 0.0% | โ |
| 7 | Running | SMX201-24 | 48 | 9 | 17 | 74 | 35.1% | 12.2% | 23.0% | more gas holes, raiser tube changed |
| 14 | Running | 640-16 | 100 | 7 | 2 | 109 | 8.3% | 6.4% | 1.8% | โ |
| 15 | Running | 640-15'' | 81 | 8 | 6 | 95 | 14.7% | 8.4% | 6.3% | rim shrinkage |
| 16 | Running | 640-17 M2 | 98 | 5 | 0 | 103 | 4.9% | 4.9% | 0.0% | โ |
| TOTAL PRODUCTION | 602 | โ | โ | โ | โ | |||||
| TOTAL REJECTION | 79 | 13.1% | 7.3% | 5.8% | โ | |||||
| ๐ฝ Machines Received from Previous Shift: | 7 | ๐ผ Machines Handed Over: | 7 |
| M/C | Issue | DownTime (min) | Action Taken | Pending Action | Responsible | Status | Odoo Notification |
|---|---|---|---|---|---|---|---|
| โ No breakdowns recorded โ | |||||||
| Die Model | Status | Remarks |
|---|---|---|
| โ No die maintenance recorded โ | ||
x-ray issue, frequent