Report #119 โ Submitted 2026-08-21 19:14:07
| No | Observation | Status |
|---|---|---|
| 1 | L15 water leaking | Low Risk |
| 2 | L7 H.F door metal stuck. | Closed |
| Furnace | Mass Received (Ton) | Consumed (Ton) | Metal Added (Ton) | Mass End of Shift (Ton) | Remarks |
|---|---|---|---|---|---|
| HA
min: 28T
|
0.00 | 0.00 | 0.00 | 0.00 | โ |
| HC
min: 24T
|
21.86 โ Below minimum
|
8.95 | 9.60 | 22.51 | โ |
| SWM1 | 32.60 | 9.60 | 10.90 | 33.90 | โ |
| SWM2 | 0.00 | 0.00 | 0.00 | 0.00 | โ |
| Stage | Condition | Comments |
|---|---|---|
| Received | Good | โ |
| Hand Over | Good | โ |
| M/C No. | Status | Mold Type | NDT OK | HC & FC Reject | NDT Reject | Total | Rejection % | H&F Rej % | NDT Rej % | Remarks |
|---|---|---|---|---|---|---|---|---|---|---|
| 4 | Running | 640 17" M2 | 105 | 5 | 0 | 110 | 4.6% | 4.6% | 0.0% | โ |
| 6 | Running | CV93 22" | 63 | 5 | 2 | 70 | 10.0% | 7.1% | 2.9% | โ |
| 7 | Running | 640 17"M1 | 95 | 5 | 1 | 101 | 5.9% | 5.0% | 1.0% | โ |
| 14 | Running | 640 16" M2 | 61 | 8 | 3 | 72 | 15.3% | 11.1% | 4.2% | โ |
| 15 | Running | 640 15" 5H | 88 | 8 | 3 | 99 | 11.1% | 8.1% | 3.0% | โ |
| 16 | Stopped | 640 16" M1 | 40 | 10 | 17 | 67 | 40.3% | 14.9% | 25.4% | continues reject (S/S) |
| TOTAL PRODUCTION | 519 | โ | โ | โ | โ | |||||
| TOTAL REJECTION | 67 | 12.9% | 7.9% | 5.0% | โ | |||||
| ๐ฝ Machines Received from Previous Shift: | 5 | ๐ผ Machines Handed Over: | 5 |
| M/C | Issue | DownTime (min) | Action Taken | Pending Action | Responsible | Status | Odoo Notification |
|---|---|---|---|---|---|---|---|
| โ No breakdowns recorded โ | |||||||
| Die Model | Status | Remarks |
|---|---|---|
| SMX211 24" | Completed | โ |
| SMX201 24" | Completed | โ |
Couldn't start L5 (CA90 26") due to X-ray 03 gripper problem.