Report #154 โ Submitted 2026-09-09 07:04:34
| No | Observation | Status |
|---|---|---|
| 1 | Safety sing in HA Furnace | Closed |
| 2 | 5s in casting line | Closed |
| 3 | Place all the cooling pips in an orderly manner | Closed |
| Furnace | Mass Received (Ton) | Consumed (Ton) | Metal Added (Ton) | Mass End of Shift (Ton) | Remarks |
|---|---|---|---|---|---|
| HA
min: 28T
|
0.00 | 0.00 | 0.00 | 0.00 | โ |
| HC
min: 24T
|
27.20 | 6.50 | 0.00 | 20.70 | โ |
| SWM1 | 27.00 | 0.00 | 8.00 | 35.00 | โ |
| SWM2 | 0.00 | 0.00 | 0.00 | 0.00 | โ |
| Stage | Condition | Comments |
|---|---|---|
| Received | Acceptable | โ |
| Hand Over | Acceptable | โ |
| M/C No. | Status | Mold Type | NDT OK | HC & FC Reject | NDT Reject | Total | Rejection % | H&F Rej % | NDT Rej % | Remarks |
|---|---|---|---|---|---|---|---|---|---|---|
| 4 | Running | 640-17 M1 | 100 | 5 | 4 | 109 | 8.3% | 4.6% | 3.7% | โ |
| 6 | Running | 640-17 M2 | 100 | 5 | 2 | 107 | 6.5% | 4.7% | 1.9% | โ |
| TOTAL PRODUCTION | 216 | โ | โ | โ | โ | |||||
| TOTAL REJECTION | 16 | 7.4% | 4.6% | 2.8% | โ | |||||
| ๐ฝ Machines Received from Previous Shift: | 2 | ๐ผ Machines Handed Over: | 2 |
| M/C | Issue | DownTime (min) | Action Taken | Pending Action | Responsible | Status | Odoo Notification |
|---|---|---|---|---|---|---|---|
| โ No breakdowns recorded โ | |||||||
| Die Model | Status | Remarks |
|---|---|---|
| BORO | Completed | โ |