GENERAL INFORMATION
Date:
2026-06-06
Shift:
Night
Supervisor:
OMAR
Team:
B
Total Attendance:
14
Total Absent:
6
โš ๏ธ
SAFETY OBSERVATIONS
NoObservationStatus
1 small size wheels fell down from Robot gripper Medium Risk
๐Ÿ”ฅ
FURNACE STATUS
Furnace Mass Received (Ton) Consumed (Ton) Metal Added (Ton) Mass End of Shift (Ton) Remarks
HA
min: 28T
28,000.00 2,470.00 0.00 25,530.00 โ€”
HC
min: 24T
0.00 0.00 0.00 0.00 โ€”
SWM1 0.00 0.00 0.00 0.00 โ€”
SWM2 0.00 0.00 0.00 0.00 โ€”
๐ŸŒŠ
LAUNDER CONDITION
StageConditionComments
Received Bad Launder Full of Metal (Jammed).
Hand Over Bad 3/4 Launder Cleaned (HA to HC).
๐Ÿญ
CASTING PRODUCTION
M/C No. Status Mold Type NDT OK HC & FC Reject NDT Reject Total Rejection % H&F Rej % NDT Rej % Remarks
6 Running 640-17" 43 5 0 48 10.4% 10.4% 0.0% โ€”
16 Running 640-15" 33 7 1 41 19.5% 17.1% 2.4% โ€”
17 Running SMX201-22-m4" 30 5 0 35 14.3% 14.3% 0.0% โ€”
18 Running CV98-20 12 5 0 17 29.4% 29.4% 0.0% โ€”
TOTAL PRODUCTION 141 โ€”โ€”โ€”โ€”
TOTAL REJECTION 23 16.3% 15.6% 0.7% โ€”
๐Ÿ”ง
MACHINE BREAKDOWN REPORT
M/CIssueDownTime (min)Action TakenPending ActionResponsibleStatusOdoo Notification
โ€” No breakdowns recorded โ€”
๐Ÿ› ๏ธ
DIE MAINTENANCE PLAN
Die ModelStatusRemarks
640-16" Completed โ€”