تقرير رقم #38 — أُرسل في 2026-06-22 06:55:55
| No | الملاحظة | الحالة |
|---|---|---|
| — لا توجد ملاحظات مسجلة — | ||
| الفرن | الكتلة المستلمة (طن) | المستهلك (طن) | المعدن المضاف (طن) | الكتلة عند نهاية الوردية (طن) | ملاحظات |
|---|---|---|---|---|---|
| HA
min: 28T
|
28.00 | 6.12 | 0.00 | 21.88 | we found havy dross inside the HA so we done the cleaning prosses |
| HC
min: 24T
|
14.80 ⚠ أقل من الحد الأدنى
|
0.00 | 0.00 | 14.80 | no pump |
| SWM1 | 0.00 | 0.00 | 0.00 | 0.00 | — |
| SWM2 | 0.00 | 0.00 | 0.00 | 0.00 | — |
| المرحلة | الحالة | التعليقات |
|---|---|---|
| الاستلام | سيئة | work is going on for repair from HA to HC half complete From HA to SWM2 not start yet |
| التسليم | سيئة | work is going on for repair from HA to HC half complete From HA to SWM2 not start yet -- extra launder fix to transfer the metal for taping |
| رقم الماكينة | الحالة | نوع القالب | NDT سليم | رفض HC و FC | رفض NDT | الإجمالي | نسبة الرفض % | نسبة رفض H&F % | نسبة رفض NDT % | ملاحظات |
|---|---|---|---|---|---|---|---|---|---|---|
| 5 | تعمل | 640-15" | 26 | 5 | 2 | 33 | 21.2% | 15.2% | 6.1% | stop at 10 PM |
| 6 | تعمل | 640-17"-m2 | 52 | 7 | 2 | 61 | 14.8% | 11.5% | 3.3% | stop at 10:00pm -- start again 4:30am |
| 7 | متوقفة | 640-17-m1 | 60 | 7 | 1 | 68 | 11.8% | 10.3% | 1.5% | stop at 10:00pm -- start again 2:30 am |
| 14 | متوقفة | r62-8" | 31 | 4 | 1 | 36 | 13.9% | 11.1% | 2.8% | stop at 10 PM |
| 16 | تعمل | 640-16"-m2 | 61 | 7 | 1 | 69 | 11.6% | 10.1% | 1.5% | stop at 10:00pm -- start again 3:30am |
| إجمالي الإنتاج | 267 | — | — | — | — | |||||
| إجمالي الرفض | 37 | 13.9% | 11.2% | 2.6% | — | |||||
| الماكينة | العطل | وقت التوقف (دقيقة) | الإجراء المتخذ | الإجراء المعلق | المسؤول | الحالة | إشعار Odoo |
|---|---|---|---|---|---|---|---|
| laser mark 2 | scaner | 0 دقيقة | maintenance team | no | maintenance team | مغلق | yes |
| prehating machine no 1 | flaim not working contusions | 0 دقيقة | maintenance team | yes | maintenance team | قيد التنفيذ | yes |
| LPDC 4 | air pressure hose disconnected | 0 دقيقة | maintenance team inform | no | maintenance team | مغلق | yes |
| موديل القالب | الحالة | ملاحظات |
|---|---|---|
| R69-18"-M1 | مكتمل | full service |
| 640-15"-M1 | مكتمل | upper mold + 4 side molds complete |
While Shaft 5 was running, we noticed that the Holding Furnace (HA) temperature was not reaching the required 800°C. The actual temperature was around 726°C, and after each ladle transfer, the temperature dropped further to approximately 640°C or below. We inspected the HA and found a heavy buildup of dross inside the furnace. The pump was lifted to allow cleaning operations. During the inspection, we found that the impeller was not rotating. We attempted to rotate it manually, but it was completely stuck. At that stage, we suspected either a mechanical failure of the impeller or blockage caused by dross accumulation. After lifting the assembly further, we discovered a piece of metal scrap lodged in the impeller, preventing it from rotating. The scrap may have entered the area during adding element operations or while removing dross from another location inside the furnace. The cleaning was completed, the obstruction was removed, and the pump was reinstalled. Melting operations were restarted at approximately 12:30 PM. As a result of this issue, all casting machines were stopped due to insufficient metal temperature. Even after cleaning, the temperature of the first ladle remained below the required casting temperature. Therefore, the first ladle was blocked and the second ladle was used for casting operations. Root Cause (Suspected): Metal scrap became trapped in the impeller, causing it to stop rotating. Reduced circulation inside the Holding Furnace led to low metal temperature and significant temperature drops during ladle transfers. Impact: Holding Furnace temperature could not reach the required 800°C. Casting operations were interrupted. All casting machines were stopped until corrective actions were completed. Corrective Action: Pump lifted and furnace cleaned. Metal scrap removed from the impeller. Pump reinstalled and melting operations resumed. First low-temperature ladle blocked and the second ladle used for production.