Date & Shift
2026-11-06
Night โ€” Team B
TOTAL NDT OK
146
Units
TOTAL HC&FC REJECT
11
Units
H&F REJECTION %
6.88%
of total production
NDT REJECTION %
1.88%
of total production
DOWNTIME (min)
960
min
๐Ÿ“‹
GENERAL INFORMATION
Date:
2026-11-06
Shift:
Night
Supervisor:
Saud
Team:
B
Total Attendance:
10
Total Absent:
5
Was the Lean Meeting conducted?:
No
โš ๏ธ
SAFETY OBSERVATIONS
NoObservationStatus
1 5s complete Closed
๐Ÿ”ฅ
FURNACE STATUS
Furnace Mass Received (Ton) Consumed (Ton) Metal Added (Ton) Mass End of Shift (Ton) Remarks
HA
min: 28T
0.00 0.00 0.00 0.00 โ€”
HC
min: 24T
17.00
โš  Below minimum
3,690.00 9,040.00 5,367.00 โ€”
SWM1 27.80 9,040.00 2,054.00 -6,958.20 โ€”
SWM2 0.00 0.00 0.00 0.00 โ€”
๐ŸŒŠ
LAUNDER CONDITION
StageConditionComments
Received Acceptable โ€”
Hand Over Acceptable โ€”
๐Ÿญ
CASTING PRODUCTION
M/C No. Status Mold Type NDT OK HC & FC Reject NDT Reject Total Rejection % H&F Rej % NDT Rej % Remarks
6 Running 666-17 78 6 1 85 8.2% 7.1% 1.2% โ€”
7 Breakdown R62-19 12 0 0 12 0.0% 0.0% 0.0% โ€”
17 Stopped R62-17 20 3 1 24 16.7% 12.5% 4.2% โ€”
17 Running R62-16 36 2 1 39 7.7% 5.1% 2.6% โ€”
TOTAL PRODUCTION 160 โ€”โ€”โ€”โ€”
TOTAL REJECTION 14 8.8% 6.9% 1.9% โ€”
๐Ÿ”ง
MACHINE BREAKDOWN REPORT
๐Ÿ”ฝ Machines Received from Previous Shift: 3 ๐Ÿ”ผ Machines Handed Over: 2
M/CIssueDownTime (min)Action TakenPending ActionResponsibleStatusOdoo Notification
HT Quenching lifter 240 min Solved โ€” Maintenance Closed โ€”
Casting L7 stopped 720 min Under maintenance โ€” Maintenance Open โ€”
๐Ÿ› ๏ธ
DIE MAINTENANCE PLAN
Die ModelStatusRemarks
โ€” No die maintenance recorded โ€”