Report #63 โ Submitted 2026-07-22 23:57:18
| No | Observation | Status |
|---|---|---|
| 1 | Waste gloves througed in the machine | Low Risk |
| 2 | Screw not install properly to the mould in the machine | Medium Risk |
| 3 | The forklift in melting without AC | Medium Risk |
| Furnace | Mass Received (Ton) | Consumed (Ton) | Metal Added (Ton) | Mass End of Shift (Ton) | Remarks |
|---|---|---|---|---|---|
| HA
min: 28T
|
21.50 โ Below minimum
|
6.90 | 13.00 | 27.60 | โ |
| HC
min: 24T
|
24.90 | 9.10 | 6.90 | 22.70 | โ |
| SWM1 | 0.00 | 0.00 | 0.00 | 0.00 | โ |
| SWM2 | 0.00 | 0.00 | 0.00 | 0.00 | โ |
| Stage | Condition | Comments |
|---|---|---|
| Received | Acceptable | โ |
| Hand Over | Good | โ |
| M/C No. | Status | Mold Type | NDT OK | HC & FC Reject | NDT Reject | Total | Rejection % | H&F Rej % | NDT Rej % | Remarks |
|---|---|---|---|---|---|---|---|---|---|---|
| 4 | Running | 640-17" M1 | 96 | 6 | 3 | 105 | 8.6% | 5.7% | 2.9% | โ |
| 6 | Running | 640-17" M2 | 81 | 6 | 7 | 94 | 13.8% | 6.4% | 7.5% | โ |
| 7 | Running | Boro 112 | 19 | 3 | 0 | 22 | 13.6% | 13.6% | 0.0% | Start 4:30 PM |
| 14 | Running | SMX201-22" M 7 | 17 | 10 | 7 | 34 | 50.0% | 29.4% | 20.6% | Stopped and started twice in shift |
| 15 | Running | CV 98-20" M 2 | 55 | 7 | 7 | 69 | 20.3% | 10.1% | 10.1% | โ |
| 16 | Stopped | 666-17" 5H | 30 | 10 | 7 | 47 | 36.2% | 21.3% | 14.9% | HighRej |
| TOTAL PRODUCTION | 371 | โ | โ | โ | โ | |||||
| TOTAL REJECTION | 73 | 19.7% | 11.3% | 8.4% | โ | |||||
| M/C | Issue | DownTime (min) | Action Taken | Pending Action | Responsible | Status | Odoo Notification |
|---|---|---|---|---|---|---|---|
| Convyour | stopped | 60 min | Infrm maintenance | NA | Maintenance | Closed | โ |
| Die Model | Status | Remarks |
|---|---|---|
| 777-17" | Completed | โ |