Report #71 โ Submitted 2026-07-25 19:00:12
| No | Observation | Status |
|---|---|---|
| 1 | metal splash to forklift operator while charging wheel to HA furnace | High Risk |
| Furnace | Mass Received (Ton) | Consumed (Ton) | Metal Added (Ton) | Mass End of Shift (Ton) | Remarks |
|---|---|---|---|---|---|
| HA
min: 28T
|
18.90 โ Below minimum
|
8.05 | 10.40 | 21.25 | โ |
| HC
min: 24T
|
19.55 โ Below minimum
|
10.50 | 8.05 | 17.10 | โ |
| SWM1 | 0.00 | 0.00 | 0.00 | 0.00 | โ |
| SWM2 | 0.00 | 0.00 | 0.00 | 0.00 | โ |
| Stage | Condition | Comments |
|---|---|---|
| Received | Acceptable | HA to SWM2 bad ( metal solidify) |
| Hand Over | Acceptable | HA to SWM2 bad ( metal solidify) |
| M/C No. | Status | Mold Type | NDT OK | HC & FC Reject | NDT Reject | Total | Rejection % | H&F Rej % | NDT Rej % | Remarks |
|---|---|---|---|---|---|---|---|---|---|---|
| 4 | Running | cv98-20 | 65 | 4 | 1 | 70 | 7.1% | 5.7% | 1.4% | โ |
| 6 | Stopped | 640-17 | 15 | 0 | 0 | 15 | 0.0% | 0.0% | 0.0% | โ |
| 7 | Running | 640-17 | 94 | 4 | 1 | 99 | 5.1% | 4.0% | 1.0% | โ |
| 14 | Running | 640-16 | 100 | 4 | 1 | 105 | 4.8% | 3.8% | 1.0% | โ |
| 15 | Running | 640-15 | 85 | 5 | 7 | 97 | 12.4% | 5.2% | 7.2% | โ |
| 16 | Running | 640-16'' | 84 | 8 | 5 | 97 | 13.4% | 8.3% | 5.2% | โ |
| TOTAL PRODUCTION | 483 | โ | โ | โ | โ | |||||
| TOTAL REJECTION | 40 | 8.3% | 5.2% | 3.1% | โ | |||||
| M/C | Issue | DownTime (min) | Action Taken | Pending Action | Responsible | Status | Odoo Notification |
|---|---|---|---|---|---|---|---|
| โ No breakdowns recorded โ | |||||||
| Die Model | Status | Remarks |
|---|---|---|
| โ No die maintenance recorded โ | ||
metal delays due to temperature variation in degassing area